Demolition, Excavation and Civil Works at Il-Pjazzetta Development located on Tower Road, Sliema.
Description of the works
CONSTRUCTION METHODOLGY
- Demolition works
- Stabilization of existing Façade to allow excavation and construction works to be carried out. Restoration of said Façade
- Excavation Works
- Civil works including permanently buried service ducts and pipes, including drainage runs and building of sealed pool structure.
- Waterproofing works to Building Structure and Landscaped Areas to achieve water tight structures.
- All ancillary works related to the construction phases as outlined by local Laws and conditions as included in the MEPA Permit
PROJECT DETAILS
Categories: | |
Client: | Gasan Enterprises Limited |
Location: | Sliema |
Completed: | 2019, Duration of the Works 40 months |
Architect: | Martin Xuereb & Associates |